The east wall of The Albert is built from about 75 pieces of carved stone. Some of them weigh up to 13,000 pounds. They hung on the front of the Ford Twin Cities Assembly Plant starting in the 1920s, came down when the plant was demolished, and sat stored on the site until Ryan Companies set them back into a new building at Ford Parkway and Cretin Avenue.
That wall and the plaza in front of it, now called Civic Square, opened at a ribbon-cutting on September 29. The Pioneer Press noted the timing: 101 years after the plant opened and 15 years after it closed. The corner Highland Park residents pass most often now has a finished entrance into the 122-acre development. The oldest material on the site arrived there first. The storefronts behind it are still empty.
Stone That Waited 15 Years for a Wall
Albert Kahn, a Detroit architect who designed industrial buildings with his brother Julius, designed the Ford plant. The new four-story apartment building takes its name from him. The plant ran for 86 years in Highland Park and closed in 2011, according to the Highland Villager.
The stone came late in the design. In a September Q&A with Finance & Commerce, Ryan's director of real estate development, Sean Ryan, described the facade as "a Hellenistic Greek style architecture developed by Albert Kahn." He said the team worked with historical societies to match old photographs of the plant. He was candid about the schedule:
"It was a fairly late addition in terms of when the construction and design team would have liked to know that we were adding 13,000-pound stones to their facade... the design team would have loved to know it six months in advance."
The cleaning was careful too. Crews used only pressurized water, because acid might have marked the stone. The restored facade wraps the ground-floor retail space on the building's east side and faces directly onto Civic Square.
A Circle of Friezes Where a Fountain Was Once Considered
The plaza's centerpiece is a circle holding two large friezes from the plant. Sean Ryan described them to Finance & Commerce as five-by-five stone panels, set alongside Ford cars and Ford imagery. He told the Highland Villager that a fountain was considered for the spot at one point, and the friezes went there instead.
That decision fits the rest of the site. Highland Bridge's public spaces keep pointing back to the plant. The City of Saint Paul says the name Assembly Union Park recognizes the site's industrial history and the Ford workforce. Civic Square makes the same point in stone, at the spot where most people enter from Ford Parkway.
From the corner, the route runs like this:
- The Albert's east wall. Start at Ford Parkway and Cretin and look at the rebuilt Kahn facade framing the ground-floor retail bays.
- The friezes at the center of Civic Square. The two salvaged panels sit in the circle directly in front of that wall.
- The sidewalk heading southwest. It connects the square to the large civic plaza and Highland Bridge's central water feature, according to the Highland Villager.
- The established parks beyond. Ryan lists Gateway, Uŋčí Makhá and Assembly Union parks among assets already delivered. At Uŋčí Makhá Park, the city notes a daylighted creek and a mural completed in 2024.
For anyone who has watched the site from Ford Parkway since demolition, this is the first time the edge facing the older neighborhood has a finished public room to walk through.
Behind the Facade, the Storefronts Are Waiting
When Pioneer Press photographers visited on September 30, the retail space behind the Kahn facade was empty. No restaurant, café or shop has been publicly named for The Albert's storefronts or the new one-story buildings beside it.
The amount of empty space matters. Ryan's grand-opening release lists 8,500 square feet of retail inside The Albert and three standalone retail buildings totaling 13,500 square feet, separate from the daycare building. That comes to roughly 22,000 square feet with no announced tenant. In June, the Pioneer Press reported that Highland Bridge had completed about 118,000 square feet of commercial space since 2022, including Lunds & Byerlys, a medical office building and retail inside the Marvella senior housing. The gateway block alone adds nearly a fifth on top of that, and the leases for it are still being negotiated.
| Space at the gateway | Size | Status heading into November 2026 |
|---|---|---|
| Ground-floor retail behind The Albert's Kahn facade | 8,500 sq ft | No tenant announced |
| Standalone one-story retail buildings west of The Albert | 13,500 sq ft total, per Ryan | No tenant announced. In June, Ryan said four prospects had signed letters of intent |
| Tierra Encantada, 2185 Hillcrest Drive | 13,000 sq ft | Lease signed in June. Operator lists "Opening this December" |
| Civic Square | Plaza | Open since September 29 |
Tierra Encantada, a Spanish-immersion early education provider, was the first tenant to sign on the Ford Parkway frontage. Its Highland Park location page says it opens this December and is taking early enrollments, with start dates still to be announced. The Highland Villager places it southeast of The Albert.
Why This Corner Ended Up One Story Tall
The size of the buildings shapes what kind of corner this becomes, and that size was argued over. The Pioneer Press reported that early plans for the Ford Parkway frontage called for commercial or mixed-use buildings of at least four stories, likely with housing above ground-floor retail, similar to The Albert. Ryan later asked the city to approve one-story commercial buildings, citing challenging site conditions and financing realities. The Board of Zoning Appeals denied the variance requests. After the City Council deadlocked in a tie vote, the appeal was effectively approved by default.
So the gateway has one four-story building with its historic wall, plus a row of single-story retail buildings. Sean Ryan described the timeline to the Highland Villager as "a very complex project." It included physical challenges, delays tied to market conditions, the variance fight and the work to secure tax increment financing, and groundbreaking came about 15 months before the ribbon-cutting.
City leaders spoke about the corner at the opening. Saint Paul Mayor Kaohly Her called the completed block an example of "the power of public-private collaboration" in Ryan's release. Ward 3 Council Member Saura Jost called The Albert "amazing" and the square "stunning," according to the Highland Villager, and thanked those who worked to preserve Highland history.
What Fills In Next, Past the Square
The next construction at Highland Bridge is mostly housing, which means more people living within a walk of those empty storefronts.
- Weidner Apartment Homes, Block 11. The project calls for 176 market-rate apartments and 2,000 square feet of retail northeast of the central water feature. In the September 25 Finance & Commerce Q&A, Sean Ryan said crews had started mobilizing and expected to "start moving dirt there" within about a week. He called it a milestone first planned for the start of COVID.
- Pulte rowhomes. In late September, Sean Ryan said Pulte would finish its roughly 170 rowhomes over the following six months.
- M/I Homes, phase two. M/I Homes has broken ground south of Pulte's first rowhomes on a phase Ryan put at about 150 more units.
None of these projects names a café or a shop either. Until the letters of intent Ryan described in June become signed leases with names on them, the Ford plant friezes are the main thing to see at Ford Parkway and Cretin. Tierra Encantada's December opening is the next date on the calendar for this block.
If you own in Highland and want to understand what a finished gateway and the leases still to come could mean for your block's value or your timing, Christian Klempp follows Highland Bridge closely and can walk you through it. Schedule a Consultation, and we can start with a walk around Civic Square.